Bathroom · Checklists
Bathroom Waterproofing: What to Check Before Tiling
The invisible layer that decides whether your neighbour's ceiling stays dry.
Updated 5 Nov 2026 · 1 min read
Once tiles go down, waterproofing becomes very expensive to fix. Check these points during the work, not afterwards.
The sequence
- Remove old tiles and screed down to the slab.
- Repair cracks, and seal around pipe penetrations with a polymer-modified mortar.
- Apply the waterproofing membrane (cementitious, polyurethane or liquid-applied) to the floor and at least 30 cm up the walls, and the full height in the shower area.
- Pond test: fill the floor with 2–3 cm of water for 24–48 hours and check the ceiling below.
- Lay a protective screed, slope it to the drain, then tile.
Checklist
- Floor slopes toward the drain (about 1:100). Pour water and watch it run.
- Wall–floor junctions are rounded or reinforced with tape
- Pipe sleeves and floor traps sealed
- Pond test done and photographed
- Epoxy grout in wet zones (it resists stains and water better than cement grout)
- Glass partition or a raised step to keep the shower water in
Ask your contractor
Which product, how many coats, and what warranty comes with it. Get the answer in writing.